Highway Engineering MCQ Quiz - Objective Question with Answer for Highway Engineering - Download Free PDF

Last updated on May 15, 2025

Latest Highway Engineering MCQ Objective Questions

Highway Engineering Question 1:

A cyclist riding on a level road has to turn a corner of radius 50 m. Find the maximum speed with which the cyclist can travel without the fear of skidding. Assume the co-efficient of friction between the tyres and track as 0.2. (Take acceleration due to gravity = 10 m/s2)

  1. 10 m/s
  2. 14.1 m/s
  3. 4.5 m/s
  4. 12 m/s
  5. 20 m/s

Answer (Detailed Solution Below)

Option 1 : 10 m/s

Highway Engineering Question 1 Detailed Solution

Explanation:

Concept:

While negotiating curve on road by vehicle, the required centripetal force is provided by the frictional force between the road and tyre.

Centripetal force = \(\frac{mv^2}{R}\) and the frictional force =

 For avoiding car to skid the centripetal force must be equal to the frictional force ⇒ \(\frac{mv^2}{R} =\mu mg \)   

∴ Maximum speed with which the cyclist can travel without the fear of skidding  \(v=\, \sqrt{\mu Rg}\)

Solution:

Given, Radius of corner = 50 m,  

coefficient of friction between the tires and track =  0.2,

 acceleration due to gravity = 10 m/s2

Maximum speed with which the cyclist can travel without the fear of skidding 

 \(v=\, \sqrt{\mu Rg} = \, \sqrt{0.2\times 50\times 9.81} =\, 9.9 \approx 10\) m/s

Highway Engineering Question 2:

Which of the following type of pavement marking is meant to separate the opposite streams of traffic on undivided two-way roads?

  1. Turn markings
  2. No passing zone markings
  3. Centre lines
  4. Stop lines
  5. None of the above

Answer (Detailed Solution Below)

Option 3 : Centre lines

Highway Engineering Question 2 Detailed Solution

Explanation

Centre lines

  • A dashed marking is used as a lane divider, or to indicate that a road, or a cycle path, has two-way traffic on it.
  • Centre line markings are used in a roadway meant for two-way traffic.

F3 Madhuri Engineering 01.08.2022 D3

Additional Information 

Turn markings

F3 Madhuri Engineering 01.08.2022 D4

No passing zone markings

Two-lane roads may have “no passing zones” marked with a SOLID YELLOW LINE. No passing zones are on hills or curves where you cannot see far enough ahead to pass safely. You must complete passing before you enter the no-passing zone.

F3 Madhuri Engineering 01.08.2022 D5

Stop lines

Stop line indicates the position beyond which the vehicles should not proceed when required to stop by traffic police, traffic signals or other traffic control devices. Stop lines should either be parallel to the intersecting roadway or at right angles to the approaching vehicle.

F3 Madhuri Engineering 01.08.2022 D7

Highway Engineering Question 3:

Select the correct statement :

  1. Psychological extra widening depends upon the number of traffic lanes.
  2. Mechanical extra widening depends upon the speed of vehicles.
  3. Psychological extra widening depends upon the length of wheel base.
  4. Mechanical extra widening depends upon the length of wheel base and the radius of curve.
  5. None of the above

Answer (Detailed Solution Below)

Option 4 : Mechanical extra widening depends upon the length of wheel base and the radius of curve.

Highway Engineering Question 3 Detailed Solution

Explanation:

The extra width of a carriageway that is required on a curved section of a road over and above that is required on a straight alignment is known as Extra Widening.

Mechanical widening: The widening required to account for the off-tracking due to rigidity of wheelbase is known as Mechanical widening. It can be calculated as:

\({W_m} = \frac{{n{l^2}}}{{2R}}\)

n = Number of lanes

l = length of wheelbase = 6.1 m

R = Radius of circular curve

Psychological Widening: Extra width of pavement provided for psychological reasons such as overhangs of vehicles, greater clearance for crossing, etc is known as Psychological Widening.

\({W_{ps}} = \frac{V}{{9.5\sqrt R }}\)

V = Design speed (kmph)

Highway Engineering Question 4:

The critical condition of stresses for combination of stresses in cement concrete pavement during summer is :

  1. load stress + warping stress - frictional stress
  2. load stress + warping stress
  3. load stress + warping stress + frictional stress
  4. load stress + frictional stress
  5. None of the above

Answer (Detailed Solution Below)

Option 1 : load stress + warping stress - frictional stress

Highway Engineering Question 4 Detailed Solution

Explanation:

Combination of stresses:

(i) There is no frictional stress at the corner region. Out of various wheel stresses

  • Corner stress is minimum as there is a discontinuity in both direction
  • Interior stress is maximum
  • Edge stress is in intermediate-range


(ii) Temperature stress is critical at the edge and interior and it is minimum at corner. At the corner, resistance due to weight is minimum, hence warping stress is minimum.

(iii) In combination of wheel load and temperature, edge region is mos critical, hence designing is done using edge region stress and however checking is done for corner region.  

Critical cases of stress combination:

(i) Summer mid-day: The critical stress for edge region is given by

Scritical = Sedge + Stemperature - Sfrictional

(ii) Winter, mid-day: The critical combination of stress for the edge region is given by

Scritical = Sedge + Stemperature + Sfrictional

(iii) Mid-nights: The critical combination of stress for the corner region is given by

Scritical = Sedge + Stemperature 

Highway Engineering Question 5:

Which of the following is the full form of PENT or PETN, an explosive used in tunneling and military applications?

  1. Pentane Energy Nitrate
  2. Polyethylene Nitrogen Trinitrate
  3. Pyrotechnic Explosive Nitrogen Trigger
  4. Pentaerythritol Tetranitrate

Answer (Detailed Solution Below)

Option 4 : Pentaerythritol Tetranitrate

Highway Engineering Question 5 Detailed Solution

Explanation:

  1. Pentaerythritol Tetranitrate (PETN) is a highly explosive compound used in both military and civilian applications, including tunneling operations and in the manufacturing of detonators and explosives.

  2. PETN is a powerful, stable explosive and is often used in combination with other materials for controlled demolition or blasting operations.

 Additional InformationTypes of Explosives  

  1. Dynamite: A high-energy explosive used in tunneling, effective for breaking hard rock and creating large blasts. It has a relatively quick detonation speed and is versatile for various tunneling conditions.

  2. ANFO (Ammonium Nitrate Fuel Oil): A cost-effective, stable explosive often used for bulk blasting in soft to medium rock. It’s favored for large-scale operations due to its efficiency and low cost.

  3. PETN (Pentaerythritol Tetranitrate): A highly sensitive explosive with a fast detonation velocity, used in tunneling for precise applications and where controlled blasting is required.

  4. Gelignite: Similar to dynamite but with improved stability, Gelignite is commonly used in tunneling where a high degree of control is necessary, particularly in narrow or confined spaces.

  5. TNT (Trinitrotoluene): Although less common than dynamite, TNT is used for specialized tunneling projects where a controlled, slower detonation is needed, providing predictable energy release.

Top Highway Engineering MCQ Objective Questions

The standard penetration of VG40 as stipulated by the Indian standard is a minimum of:

  1. 80.00
  2. 60.00
  3. 45.00
  4. 35.00

Answer (Detailed Solution Below)

Option 4 : 35.00

Highway Engineering Question 6 Detailed Solution

Download Solution PDF

Explanation:

As per IS 73 (2013): Paving Bitumen

The requirements for paving bitumen are as follows:

Characteristics Paving Grades
VG10 VG20 VG30 VG40
Penetration at 25°C, 100 g, 5 s, 0.1 mm, Min 80 60 45 35
Flash point (Cleveland open cup), °C, Min  220 220 220 220
Softening point (R&B), °C, Min 40 45 47 50

The maximum superelevation on hill roads should not exceed 

  1. 7%
  2. 8%
  3. 9%
  4. 10%

Answer (Detailed Solution Below)

Option 4 : 10%

Highway Engineering Question 7 Detailed Solution

Download Solution PDF

Concept:

The centrifugal force exerted on the vehicles while traversing through the curves is counteracted by providing superelevation, which is given by:​​

\( \;e = \frac{{{V^2}}}{{127R}}\)

However, it is assumed that the centrifugal force is completely nullified if the vehicle is travelling at its 75% of the vehicle design speed.

∴ \( \;e = \frac{{{(0.75V)^2}}}{{127R}} = \frac{{{V^2}}}{{225R}}\)

According to IRC,

Maximum Superelevation

Plain & Rolled Terrain

7 %

Hilly Terrain

10%

Urban Roads

4%

The interface treatment provided to plug in the voids of porous surfaces and to bond loose particles in bituminous pavements is called:

  1. tack coat
  2. seal coat
  3. prime coat
  4. surface dressing

Answer (Detailed Solution Below)

Option 3 : prime coat

Highway Engineering Question 8 Detailed Solution

Download Solution PDF

Explanation:

Prime coat:

The prime coat is an application of low viscous cutback bitumen to an absorbent surface like granular bases on which binder layer is placed. It provides bonding between two layers. Unlike the tack coat, prime coat penetrates into the layer below, plugs the voids, and forms a watertight surface. 

Prime coat

Seal Coat:

Seal Coat Seal coat is a thin surface treatment used to water-proof the surface and to provide skid resistance.

Tack coat:

Tack coat is a very light application of asphalt, usually asphalt emulsion diluted with water. It provides proper bonding between two layers of binder course and must be thin, uniformly cover the entire surface, and set very fast.

The bituminous prime coat is the first application of low viscosity liquid bituminous material over an existing porous or absorbent pavement surface like the WBM base course. 

The conventional sign shown in the figure below represent a

Assignment 17 Aditya SSC JE CE 16 4th March 2017 Evening 31 Q nitesh D1

  1. Bridge carrying railway below road.
  2. Bridge carrying road below railway
  3. Bridge carrying road and railway at the same level.
  4. A level crossing 

Answer (Detailed Solution Below)

Option 2 : Bridge carrying road below railway

Highway Engineering Question 9 Detailed Solution

Download Solution PDF

Name

Conventional Sign

Level Crossing

F1 N.M Madhu 06.03.20 D3

A bridge carrying road below railway

F1 N.M Madhu 06.03.20 D5

A bridge carrying railway below the road

 

F1 N.M Madhu 06.03.20 D6

Bridge carrying road & railway

 

F1 N.M Madhu 06.03.20 D7

Railway over road

 

F1 N.M Madhu 06.03.20 D8

Railway below road

 

F1 N.M Madhu 06.03.20 D9

What will be the theoretical maximum capacity (to nearest 10 units) for a single lane of highways given that the speed of the traffic stream is 40 km/hr

  1. 3000 veh/hr
  2. 2860 veh/hr
  3. 2510 veh/hr
  4. 2010 veh/hr

Answer (Detailed Solution Below)

Option 2 : 2860 veh/hr

Highway Engineering Question 10 Detailed Solution

Download Solution PDF

Concept:

Theoretical maximum capacity is given by,

\(C = \frac{{1000\;V}}{S}\)

Where,

C = is capacity is vehicle/hr

V = speed in km/hr

S = minimum clear distance between two vehicles

∴ S = 0.2 V + 6 ( if V is in kmph ) 

(or) S = 0.7 v + 6 ( if v is in m/s )

Calculation:

Given,

Velocity (V) = 40 kmph

∵ S = 0.2 V + 6 = 0.2 × 40 + 6 = 14 m

Theoretical Maximum capacity is given by,

\(C = \frac{{1000\;V}}{S}\)

\(C = \frac{{1000\; \times \ 40}}{14}\)

C = 2857.142 Veh/hr ≈ 2860 veh/hr

Calculate the lag distance for design speed of 47 km/h for two-way traffic on a single-lane road (assume coefficient of friction as 0.38 and reaction time of driver as 2.5 seconds)

  1. 32.64 m
  2. 111.04 m
  3. 55.52 m
  4. 65.28 m

Answer (Detailed Solution Below)

Option 4 : 65.28 m

Highway Engineering Question 11 Detailed Solution

Download Solution PDF

Concept:

Lag distance = 0.278 × V × tR

Where,

V = Speed in Kmph

tR = Reaction time in sec

Calculation:

Lag distance = 0.278 × 47 × 2.5 = 32.665

For two way traffic on a single lane lag distance = 2 × 32.665 = 65.33 m

The type of transition curve that is generally provided on hill road is

  1. Circular
  2. Cubic parabola
  3. Lemniscate
  4. Spiral

Answer (Detailed Solution Below)

Option 4 : Spiral

Highway Engineering Question 12 Detailed Solution

Download Solution PDF

Explanation:

Transitions curve:

(i) When a vehicle traveling on a straight road enters into a horizontal curve instantaneously, it will cause discomfort to the driver. To avoid this, it is required to provide a transition curve. This may be provided either between a tangent and a circular curve or between two branches of a compound or reverse curve.

Different types of transition curve:

The types of transition curves commonly adopted in horizontal alignment highway are

(i) Spiral or clothoid

(ii) Bernoulli’s Lemniscate

(iii) Cubic parabola

F1 Shraddha Chandra 25.01.2021 D2

(a) All the three curves follow almost the same path up to deflection angle of 4°, and practically there is no significant difference between even up to 9°. In all these curves, the radius decreases as the length increases.

(b) According to IRC ideal shape for transition curve is spiral because rate of change of radial acceleration remains constant. Generally, spiral curve provided on hilly road.

(c) Cubic parabola is provided for the railway.

A road sign indicates “No parking” is

  1. Cautionary sign
  2. Mandatory sign
  3. Informatory sign
  4. None of the above

Answer (Detailed Solution Below)

Option 2 : Mandatory sign

Highway Engineering Question 13 Detailed Solution

Download Solution PDF

Sr no.

Type of sign

Shape

Border colour

Legend colour

Background colour

1.

Mandatory sign(Regulatory sign)

Circular

Red

Black

white

2.

Cautionary sign(warning sign)

Upward triangle

Red

Black

White

3.

Informatory sign

Rectangle

use of unique design and different colours.

 Mandatory Sign (Regulatory sign) → Ex:- Give way, no entry, Stop, No parking

No parking

Cautionary sign(warning sign→ Ex:- Narrow road, narrow bridge.

Narrow road

Informatory sign → Ex:- Parking, bus stop

Parking

According to Indian standards, VG30 grade of Bitumen is suitable for which of the following 7-day average maximum air temperature ranges?

  1. 20 – 30
  2. 38 – 45
  3. 30 – 38
  4. 45 – 53

Answer (Detailed Solution Below)

Option 2 : 38 – 45

Highway Engineering Question 14 Detailed Solution

Download Solution PDF

Explanation

The range of paving bitumen is suitable for 7 days Average Maximum Air Temperature is given below(IS 73: 2013, C:5):

                   Range                    Suitable for 7 days average maximum air Temperature oc
VG10 <30
VG20 30-38
VG30 38-45
VG40 >45

The ‘Peak hour factor’ is defined as the ratio between the number of vehicles counted during the peak hour and _______ the number counted during the highest fifteen consecutive minutes.

  1. Five times
  2. Ninety-eight times.
  3. Thirty times.
  4. Four times.

Answer (Detailed Solution Below)

Option 4 : Four times.

Highway Engineering Question 15 Detailed Solution

Download Solution PDF

Concept:

Peak Hour Factor (PHF):

It compares the traffic volume during the busiest 15 minutes of the peak hour with the total volume during the peak hour. It indicates how consistent traffic volume is during the peak hour.

\(Peak\space Hour\space Factor(PHF)= {Total\space hourly \space volume \over Peak\space 15\space minute\space volume\space within\space the\space hour \times 4}\)

The Highway Capacity Manual advises that in absence of field measurements reasonable approximations for peak hour factor can be made as follows:

  • 0.95 for congested condition
  • 0.92 for urban areas
  • 0.88 for rural areas 

Hence, The ‘Peak hour factor’ is defined as the ratio between the number of vehicles counted during the peak hour and four times the number counted during the highest fifteen consecutive minutes.

Get Free Access Now
Hot Links: teen patti joy vip teen patti dhani teen patti gold online