Download Solution PDFUsually, the expenditure on supervision charges is ________ of the total cost.
This question was previously asked in
SSC JE Electrical 4 Dec 2023 Official Paper II
Answer (Detailed Solution Below)
Option 4 : 1% to 1.5%
Free Tests
View all Free tests >
RRB JE CBT I Full Test - 23
14.2 K Users
100 Questions
100 Marks
90 Mins
Detailed Solution
Download Solution PDFExplanation:
- The correct answer is 4) 1% to 1.5%. Expenditure on supervision charges typically ranges from 1% to 1.5% of the total cost.
- Supervision charges encompass the costs associated with overseeing and managing construction projects, including monitoring progress, ensuring compliance with specifications, and coordinating various tasks.
- This percentage allocation is a common industry standard, reflecting the importance of effective supervision in ensuring the successful and timely completion of construction projects while maintaining cost efficiency.
- However, actual percentages can vary based on project complexity, scale, and other factors influencing the level of supervision required.
Last updated on Jun 16, 2025
-> SSC JE Electrical 2025 Notification will be released on June 30 for the post of Junior Engineer Electrical/ Electrical & Mechanical.
-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.
-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31.
-> Candidates with a degree/diploma in engineering are eligible for this post.
-> The selection process includes Paper I and Paper II online exams, followed by document verification.
-> Prepare for the exam using SSC JE EE Previous Year Papers.