If 6 men and 8 boys can do a piece of work in 10 days, while 26 men and 48 boys can do the same in 2 days, the time taken by 25 boys in doing the same type of work will be:

This question was previously asked in
RRB Technician Grade III Official Paper (Held On: 28 Dec, 2024 Shift 1)
View all RRB Technician Papers >
  1. 6 days
  2. 4 days
  3. 5 days
  4. 8 days

Answer (Detailed Solution Below)

Option 4 : 8 days
Free
RRB Technician Grade 3 Full Mock Test
2.6 Lakh Users
100 Questions 100 Marks 90 Mins

Detailed Solution

Download Solution PDF

Given:

6 men and 8 boys can do a piece of work in 10 days.

26 men and 48 boys can do the same work in 2 days.

Formula Used:

Work done (W) = Number of workers × Time

Calculation:

Let's assume 1 man's 1 day work = M and 1 boy's 1 day work = B.

We have two equations:

6M + 8B = W/10 ⇒ 60M + 80B = W ---- (1)

26M + 48B = W/2 ⇒ 52M + 96B = W ---- (2)

Equating both equations:

60M + 80B = 52M + 96B

⇒ 8M = 16B

⇒ M = 2B

Substituting M = 2B in equation (1):

60(2B) + 80B = W

⇒ 120B + 80B = W

⇒ 200B = W

Now, we need to find the time taken by 25 boys to complete the work:

Work done by 25 boys in 1 day = 25B

Total Work = 200B

Time taken by 25 boys = Total Work / Work done per day

⇒ Time = 200B / 25B

⇒ Time = 8 days

The correct answer is option 4.

Latest RRB Technician Updates

Last updated on Jun 16, 2025

-> The RRB Technician 2025 Vacancies have been announced in the Employment Newspaper.

-> As per the Notice, around 6180 Vacancies will be announced for the Technician 2025 Recruitment. 

-> The Online Application form for RRB Technician will be open from 28th June 2025 to 28th July 2025. 

-> The Pay scale for RRB Technician posts ranges from Rs. 19900 - 29200.

-> Prepare for the exam with RRB Technician Previous Year Papers.

More MDH Questions

More Time and Work Questions

Get Free Access Now
Hot Links: lucky teen patti happy teen patti teen patti joy 51 bonus teen patti gold old version