A and B working alone can do a work in 40 days and 30 days, respectively. They started the work together, but B left after some time and A finished the remaining work in 5 days. How many days after starting did B leave the work?

This question was previously asked in
RRB Technician Grade III Official Paper (Held On: 28 Dec, 2024 Shift 2)
View all RRB Technician Papers >
  1. 12 days 
  2. 14 days 
  3. 16 days 
  4. 15 days 

Answer (Detailed Solution Below)

Option 4 : 15 days 
Free
RRB Technician Grade 3 Full Mock Test
2.6 Lakh Users
100 Questions 100 Marks 90 Mins

Detailed Solution

Download Solution PDF

Given: 

A and B can do a work in 40 and 30 days respectively.

A and B began the work together.

After some days B left, A finished the remaining in 5 days

Concept used:

Efficiency = (Total work / Total time taken)

Efficiency = work done in a single day 

Calculation:

Let, after x days B leave.

Let the total work is the 120 units (LCM of 30 and 40)

Efficiency of A is 120 / 40 = 3 units

Efficiency of B is 120 / 30 = 4 units

So, for x days they both work together.

According to the question,

(3 + 4) × x + 5 × 3 = 120

⇒ 7x + 15 = 120

⇒ x = 15 days

∴ B leaves after 15 days.

Additional Information

Efficiency of a person is inversely proportional to number of days to complete the work.

Latest RRB Technician Updates

Last updated on Jun 27, 2025

-> The RRB Technician 2025 Vacancies have been released in the CEN Short Notification - 02/2025.

-> As per the Notice, around 6238 Vacancies is  announced for the Technician 2025 Recruitment. 

-> The Online Application form for RRB Technician will be open from 28th June 2025 to 28th July 2025. 

-> The Pay scale for RRB Technician posts ranges from Rs. 19900 - 29200.

-> Prepare for the exam with RRB Technician Previous Year Papers.

More Work Efficiency Questions

More Time and Work Questions

Get Free Access Now
Hot Links: teen patti comfun card online teen patti plus teen patti master 2024 teen patti 500 bonus teen patti boss