Download Solution PDFThe material supported by a retaining wall kept above the horizontal plane at the elevation of the top of the retaining wall is known as:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFSurcharge: This term refers to the additional load or weight supported by a retaining wall, which is kept above the horizontal plane at the elevation of the top of the retaining wall. Surcharge could include anything that adds to the weight of the soil behind the retaining wall, such as an additional layer of soil, vehicles, structures, or other loads.
Backfill: The material used to refill an excavation or the material placed behind a retaining wall is called backfill, but it is not specifically the material above the horizontal plane of the wall.
Infill: This refers to materials used to fill in gaps or spaces, often between structural elements, but is not specifically related to retaining walls.
Debris: This term generally refers to loose fragments or waste material but is not used to describe the material supported by a retaining wall.
Last updated on May 28, 2025
-> SSC JE notification 2025 for Civil Engineering will be released on June 30.
-> Candidates can fill the SSC JE CE application from June 30 to July 21.
-> The selection process of the candidates for the SSC Junior Engineer post consists of Paper I, Paper II, Document Verification, and Medical Examination.
-> Candidates who will get selected will get a salary range between Rs. 35,400/- to Rs. 1,12,400/-.
-> Candidates must refer to the SSC JE Previous Year Papers and SSC JE Civil Mock Test, SSC JE Electrical Mock Test, and SSC JE Mechanical Mock Test to understand the type of questions coming in the examination.
-> The Staff Selection Commission conducts the SSC JE exam to recruit Junior Engineers in different disciplines under various departments of the Central Government.