Download Solution PDF14 persons can sink a tubewell in 12 days. How many extra persons are required to sink the tubewell in 8 days?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
14 persons can sink a tubewell in 12 days.
Time required to sink the tubewell = 8 days.
Formula used:
Work = Number of persons × Number of days
To sink the tubewell in 8 days, we calculate the total number of persons required.
Calculation:
Work done by 14 persons in 12 days = Work done by total persons required in 8 days.
⇒ 14 × 12 = Total persons required × 8
⇒ Total persons required = (14 × 12) ÷ 8
⇒ Total persons required = 21
Extra persons required = Total persons required - Initial persons
⇒ Extra persons required = 21 - 14
⇒ Extra persons required = 7
∴ The correct answer is option (2).
Last updated on Jun 7, 2023
The West Bengal Central School Service Commission (WBSSC) is soon expected to release a notification for the recruitment of Group C posts under the University of Calcutta. The recruitment is anticipated to offer around 3000 vacancies for clerks and other non-teaching staff. Candidates interested in applying for these positions must be aged between 18 and 45 years. The selection process will involve a Written Test and Skill Test to assess the candidates' performance.