Measurement MCQ Quiz - Objective Question with Answer for Measurement - Download Free PDF
Last updated on May 26, 2025
Latest Measurement MCQ Objective Questions
Measurement Question 1:
The quantity of flooring is measured in:
Answer (Detailed Solution Below)
Measurement Question 1 Detailed Solution
Explanation:
-
Flooring quantity is measured in square meters (m²), which represents the area of the floor.
-
The length and breadth for measuring the flooring are taken as the inside dimensions of the room, from wall to wall of the superstructure. This ensures that the area being measured corresponds to the floor space inside the walls where the flooring material is applied.
-
Height is generally not involved in the calculation of flooring area unless there is a requirement for volume calculations, such as in the case of raised floors or for materials like concrete flooring.
Additional InformationTypes of Flooring Measurements:
-
For tiled flooring, the measurement is based on the total area covered by tiles, excluding any spaces like doorways or areas not covered by the flooring.
-
For wooden or vinyl flooring, measurements are usually taken from wall to wall, inside the room, and may include allowances for any cutting or wastage.
-
For raised flooring, the area may be calculated similarly to conventional flooring but might involve adjustments if the height of the floor needs to be factored into the design or material estimate.
Measurement Question 2:
If the length, width and height of the wall is 7 m, 0.3 m, 3 m, respectively, then the total quantity of brickwork required will be:
Answer (Detailed Solution Below)
Measurement Question 2 Detailed Solution
Explanation:
To calculate the total quantity of brickwork, we need to find the volume of the wall. The volume is calculated by multiplying the length, width, and height of the wall.
Given:
-
Length = 7 m
-
Width = 0.3 m
-
Height = 3 m
Formula
Volume = Length × Width × Height
Substitute the values:
Volume = 7 m × 0.3 m × 3 m = 6.3 m³
So, the total quantity of brickwork required is 6.3 m³.
Measurement Question 3:
As per IS 1200 Part I, the measurement of:
Answer (Detailed Solution Below)
Measurement Question 3 Detailed Solution
Explanation:
As per IS 1200 Part I, which deals with the measurement of building works, the measurement guidelines are:
-
Length: To be measured to the nearest 0.01 meters (1 cm).
-
Area: To be measured to the nearest 0.01 square meters (1 cm²).
-
Volume: To be measured to the nearest 0.01 cubic meters (10 liters).
Additional InformationIS 1200 Part I - General Principles of Measurement of Works in Building Construction:
-
Purpose:
-
IS 1200 Part I provides the standard methods for measurement in building construction to ensure uniformity and consistency in the way work is measured and reported.
-
It helps avoid discrepancies in quantity calculation and provides guidelines for accurate recording of measurements on construction sites.
-
- Application:
-
IS 1200 Part I is applicable to all building works, including residential, commercial, industrial, and infrastructural projects.
-
It is used by contractors, engineers, quantity surveyors, and project managers to ensure that the work is measured consistently and in accordance with established norms.
Measurement Question 4:
The plinth area of a building is measured at which level?
Answer (Detailed Solution Below)
Measurement Question 4 Detailed Solution
Explanation:
(as per IS 3861:2002 – Method of Measurement of Plinth, Carpet, and Rentable Areas of Buildings):
-
According to IS 3861:2002, the plinth area of a building is defined as the built-up covered area measured at the floor level of the basement or any storey.
-
In common construction practice, it is measured at the floor level of the ground floor, which is the finished floor level of the building.
Additional Information.
-
Top of the damp-proof course
-
It is a moisture barrier just above the ground level.
-
-
Mid-level of the foundation
-
The foundation level is beneath the ground and not the reference point for measuring plinth area.
-
-
Top of the plinth
-
The top of the plinth refers to the level at the top of the foundation wall or base, but the plinth area measurement is considered at the top of the damp-proof course.
-
Measurement Question 5:
Following items are measured in kg.
Answer (Detailed Solution Below)
Measurement Question 5 Detailed Solution
Concept:
According to IS 1200 (Part 8)
Wire netting used as encasement shall be described (including meshes and wires) and shall be measured in square metres.
Steel rolling shutter/grills shall be described and measured in square metres. The width shall be measured as the outer distance between the backs of the two guide channels of the rolling shutters and the height shall be the distance between the still and the centre of the hood cover.
Gates shall be described and enumerated or measured in square meters; hangings, guide rails and fastenings shall be described and included with item.
The mass of steel sheet, plate and strip: rolled steel sections. Steel rods, steel reinforcements, and steel strips; forged steel, steel casting, and steel tubes shall be taken from relevant Indian Standards. So these are measured in kg.
Site perforated pipes shall be described and measured by mass in kilogram. Deductions for perforations/slots shall, however, be made if its area exceeds 0·02 m2.
Top Measurement MCQ Objective Questions
According to SP: 27-1984, the thickness of slab or RC slab shall be measured to the nearest of:
Answer (Detailed Solution Below)
Measurement Question 6 Detailed Solution
Download Solution PDFExplanation:
General rules for measurement are:
All works shall be measured subject to the following tolerances:
(i) Dimensions shall be measured to the nearest 0.01 meter.
(ii) Areas shall be measured to the nearest 0.01 sq.m.
(iii) Cubic contents shall be worked up to the nearest 0.01 cum.
Except:
1. The woodworks should be measured nearest to 0.002 m.
2. Thickness of slab which shall be measured to the nearest 0.005 m.
3. Structural steelworks to the nearest 0.001 m.
4. Thickness of roadwork (where the thickness is less than 200 mm) to the nearest 0.005 m.
The expected out turn (cubic metre) of reinforced brickwork per mason per day is _____.
Answer (Detailed Solution Below)
Measurement Question 7 Detailed Solution
Download Solution PDFExplanation:
The capacity of doing work by artesian or skilled labour in the form of quantity of work per day is known as out turn of the labour.
Particulars of Item |
Expected out-turn (m3) |
Cement concrete (1: 2: 4) |
5.0 |
Lime concrete in foundation |
8.50 |
Reinforced Brick work |
1.00 |
R.C.C work |
3.00 |
Brickwork in lime or cement mortar in foundation and Plinth |
1.25 |
Calculate the quantity (cube m) of brick work for a room using the central line method, if the interior dimension of the room is 5 m × 4 m and height of the room is 3.5 m. The width of the wall is 300 mm and dimension of the door is 2 m × 1.2 m.
Answer (Detailed Solution Below)
Measurement Question 8 Detailed Solution
Download Solution PDFConcept:
Central line method
It is one of the methods for preparing an estimate.
Calculation of length of the wall is done first, and then multiply it with the breadth and depth of the wall to find out quantity.
This is a method that is suitable for rectangular, circular buildings having no inter or cross walls. Hence it is suitable for a wall having the same width.
Calculation:
Center to center length of wall = 5 + 0.3 = 5.3 m
Center to center width of wall = 4 + 0.3 = 4.3 m
So, Total centre line perimeter = 2 × 5.3 + 2 × 4.3 = 19.2 m
Total volume of brickwork = Total center line perimeter × width of wall × height of room - Volume of door opening
Total volume of brickwork = 19.2 × 0.3 × 3.5 – 1.2 × 2 × 0.3 = 19.44 m3Calculate the number of bags of cement required for the 12 mm thick plastering of a wall of 5 m long, 3.5 m high and 300 mm thick, if 1: 3 cement mortar is used.
Answer (Detailed Solution Below)
Measurement Question 9 Detailed Solution
Download Solution PDFConcept:
Dry volume of cement mortar = 1.33 × wet volume of cement mortar
Bulk density of cement = 1440 kg/m3
Weight of 1 bag of cement = 50 kg
Calculation:
Given, L = 5 m, H = 3.5 m, T = 0.3 m, Plaster thickness = 0.012 m
Plaster required for both side of wall = 2 × 5 × 3.5 × 0.012 = 0.42 m3
Dry volume of cement mortar = 1.33 × 0.42 = 0.5586 m3
Volume of cement required = 0.5586/4 = 0.13965 m3
Cement bags required = 0.13965/50 × 1440 = 4 bags
The expected out turn of 12 mm plastering with cement mortar is:
Answer (Detailed Solution Below)
Measurement Question 10 Detailed Solution
Download Solution PDFThe capacity of doing work by artesian or skilled labour in the form of a quantity of work per day is known as outturn of the labour.
Particulars of Item |
Expected out-turn (sq. meter) |
12 mm Plastering with cement or lime mortar |
8.0 |
Pointing with cement or lime mortar |
10.0 |
2.5 cm (1”) C.C. floor |
7.50 |
Sawing hardwood |
4.00 |
Sawing of softwood |
6.00 |
For obtaining the environmental lead for sandy track, lead is multiplied by ______.
Answer (Detailed Solution Below)
Measurement Question 11 Detailed Solution
Download Solution PDFExplanation:
Lead:
- The distance between the source of availability of material and the construction site is known as Lead
- Lead is measured in km
- The cost of conveyance of material depends on lead
The environment lead on the metalled roads are arrived at by multiplying by a factor as follows:
- For Sandy tracks – Lead × 1.4
- For metal tracks – Lead × 1.0
- For cartze tracks – Lead × 1.1
For brickwork, no deduction is made for the area of opening up to
Answer (Detailed Solution Below)
Measurement Question 12 Detailed Solution
Download Solution PDFExplanation:
Rules for the deduction for openings as per IS - 1200 for brickwork:
No deduction is made for the following:
i) Bearing of floor and roof slabs are not deducted from the masonry in the superstructure.
ii) Opening up to 0.1 m2
iii) Ends of the beam, posts, rafters, purlin, etc. chajjas where thickness does not exceeds 10 cm.
iv) Bed plates, wall plates, bearing of chajjas where thickness does not exceed 10 cm.
Deduction in plastering are made in the following manner:
i) No deduction is made for ends of beams, posts, rafters, purlin, etc.
ii) No deduction is made for opening up to 0.5 m2 and no addition is made for jambs, soffits, and sills of these openings.
iii) For opening more than 0.5 m2 and up to 3 m2 the deduction is made for one face only. No addition for jambs, soffits, and sills of these openings.
iv) For opening above 3 m2 the deduction is made for both faces of openings and the jambs, soffits, and sills shall be added.
Which one of the following shows total quantities of all the items of materials required for the completion of the construction?
Answer (Detailed Solution Below)
Measurement Question 13 Detailed Solution
Download Solution PDFExplanation:
Material statement: The total quantities of all the items of materials required for the completion of the construction is shown in Material statement.
Bar bending schedule: Bar Bending Schedule, commonly referred to as “BBS” is a comprehensive list that describes the location, mark, type, size, length and number, and bending details of each bar or fabric in a Reinforcement Drawing of a Structure.
Work charged establishment: The work charged establishment will include the temporary establishment as are employed for the execution or the immediate technical supervision or departmental stores in connection with the specific work.
Sundries: Sundries is the column used to add prices for miscellaneous items which are not listed in the bow. For example, binding wire used to tie rebar, cover blocks etc.The expected out turn (square metre) of sawing of the soft wood per mason per day is _____.
Answer (Detailed Solution Below)
Measurement Question 14 Detailed Solution
Download Solution PDFExplanation:
The quantity of work which can be done by an artisan for trade working of 8 hours is known as out - turn work.
The outturn for different types of work are as follows:
1. Sawing of softwood = 5.5 m2 per mason per day
2. Earthwork in the excavation in foundation trenches = 2.10 m3 per mason per day.
3. Cement concrete work = 5 m3 per mason per day.
4. Earthwork in the excavation in foundation = 2.75 m3 per mason per day.Calculate the quantity of the earthworks in the cubic meter for a canal embankment of 100 m long having heights of 3 m and 5 m at the two extreme edges. Top widths of the embankment are 2 m and 4 m at the two extreme edges and the side slope is 2 : 1. Use the trapezoidal method.
Answer (Detailed Solution Below)
Measurement Question 15 Detailed Solution
Download Solution PDFConcept:
The trapezoidal formula is given as,
\(V=\frac{L}{2}\left[ \left( {{A}_{1}}+{{A}_{n}} \right)+2\left( {{A}_{2}}+{{A}_{3}}+\ldots +{{A}_{n-1}} \right) \right]\)
Calculation:
The section across the embankment would be trapezoidal in shape.
For extreme edge (1): Top Width = 2 m, Heigth = 3, and
Bottom width = 2 + 2 × 3 + 2 × 3 = 14 m
\(⇒ A_1 = \frac{Top\;width+Bottom\;width}{2}× h=\frac{2+14}{2}× 3=24\;m^2\)
For extreme edge (2): Top Width = 4 m, Heigth = 5,
Bottom width = 4 + 2 × 5 + 2 × 5 = 24 m
\(⇒ A_2 = \frac{Top\;width+Bottom\;width}{2}× h=\frac{4+24}{2}× 5=70\;m^2\)
The volume of earthwork \(\Rightarrow V = \frac{L}{2}\left[ {\left( {{A_1} + {A_2}} \right)} \right]=\frac{100}{2}\left[ {\left( {{24} + {70}} \right)} \right]=4700\) m3.