Welded Joints MCQ Quiz - Objective Question with Answer for Welded Joints - Download Free PDF

Last updated on Jun 17, 2025

Latest Welded Joints MCQ Objective Questions

Welded Joints Question 1:

The symbol qImage680e08bb0c0ca2cc55c827dd refers to:

  1. Single Fillet weld
  2. Square butt weld
  3. Seam weld
  4. Single V-butt weld

Answer (Detailed Solution Below)

Option 1 : Single Fillet weld

Welded Joints Question 1 Detailed Solution

Explanation:

Welding symbol:

  • The arrow of the welding symbol indicates the point at which the weld is to be made and the line connecting the arrow to the reference line is always at an angle.
  • Whenever the basic weld symbol is placed below the reference line, the weld is made on the side where the arrow points (referred to as the arrow side).
  • Whenever the basic symbol is placed above the reference line, the weld is to be made on the other side of the joint.
  • The symbol for fillet weld is 3

Welder 20 10Q Revised Hindi - Final 3

  • Figure: (a) Fillet weld symbols shown on the bottom side of the reference line indicates that the weld is located in the same position where the arrow points.
  • Figure: (b) Fillet weld symbols shown on the upper side of the reference line indicates that the weld is on the opposite side where the arrow points.

∵ there is nothing mention about the arrow side or other side, ∴ single fillet weld will be the required answer.

Additional Information

Some of the common welding symbols is given below.

weld symbol1

111

2222

Welded Joints Question 2:

A plate 100 mm wide and 10 mm thick is welded to another plate by means of a double parallel fillet weld. The welding is done along the width of the plate. The plates are subjected to a force of 75 kN. The maximum strength of the joint in tension and shear stress is 80 MPa and 60 MPa respectively. The length of the weld without adding the length for starting and stoppage will approximately be: 

  1. 35.2 mm
  2. 44.2 mm
  3. 88.4 mm
  4. > 90.0 mm

Answer (Detailed Solution Below)

Option 3 : 88.4 mm

Welded Joints Question 2 Detailed Solution

Concept:

In Parallel Fillet Weld failure occurs because of shear and the Strength of Parallel Fillet Weld is given by

\(\tau = \frac{P}{tl} = \frac{P}{0.707nhl}\)

where \(\tau\) = Shear Strength of Joint, P = Force Acting on the Plate, h = leg of the weld, t = throat of the weld, l = length of the weld, n = no of weld

Calculation:

Given:

h = 10 mm, b = 100 mm, P = 75 kN, \(\tau\) = 60 MPa, \(\sigma\) = 80 MPa, n = 2 (Double Parallel Fillet Weld)

MD final images Q6

In a double parallel fillet weld, two lines of welding are to be provided. Hence each line shares a load of 

\(F = \frac{P}{2 } = \frac{75}{2}\)

F = 37.5 kN = 37500 N

\(F = 0.707\tau nhl\)

37500 = 0.707 × 60 × 106  × 10 × 10-3 × l

l = 88.4 mm

Welded Joints Question 3:

Consider a single V-groove butt welded joint between two plates of the same thickness equal to 6 mm and the same width of 60 mm is subjected to a tensile force of 36 kN. Assuming that the weld throat dimension is the same as the thickness of the plate, then the average normal stress induced in the joint is equal to?

  1. 50 MPa
  2. 100 MPa
  3. 150 MPa
  4. 200 MPa

Answer (Detailed Solution Below)

Option 1 : 50 MPa

Welded Joints Question 3 Detailed Solution

Concept:

The weld strength formula for V-groove or double butt joint is:

\(P = (t_1+t_2)\times l\times σ_t\)

where t1 and t2 are the thickness of the plate, l is the length of the plate, P is the tensile force, and σt is the normal stress.

Calculation:

Given:

t1 = t2 = 6 mm, l = 60 mm, P = 36 kN

\(\sigma_t = \frac{P}{2t\times l}\)

\(\sigma_t = \frac{36000}{2\times 0.6\times 6} = 50 \ MPa\)

Welded Joints Question 4:

Identify the toe crack from the given figure.

F2 Madhuri Engineering 28.07.2022 D2

  1. B
  2. A
  3. C
  4. D

Answer (Detailed Solution Below)

Option 3 : C

Welded Joints Question 4 Detailed Solution

Explanation:

Welding defects:

  • Cracks
  • Cavities
  • Solid inclusions
  • Incomplete fusion
  • Imperfect shape or unacceptable contour

 

Welding cracks:

Fracture-type interruptions either in the weld or in base metal adjacent to the weld.

Serious defect because it is a discontinuity in the metal that significantly reduces strength.

Caused by embrittlement or low ductility of weld and/or base metal combined with high restraint during contraction.

In general, this defect must be repaired.

F2 Madhuri Engineering 28.07.2022 D3

Cavities:

Two defect types, similar to defects found in castings:

1. Porosity - Small voids in weld metal formed by gases entrapped during solidification. Caused by the inclusion of atmospheric gases, sulfur in the weld metal, or surface contaminants.

2. Shrinkage voids - Cavities formed by shrinkage during solidification.

Solid inclusion:

Nonmetallic material is entrapped in the weld metal. A most common form is slag inclusions generated during AW processes that use flux. Instead of floating on top of the weld pool, globules of slag become encased during solidification.

Incomplete fusion:

A weld bead in which fusion has not occurred throughout the entire cross-section of the joint.

Welded Joints Question 5:

Time of current flow through the work piece till they are heated to require temperature is known as?

  1. Hold time
  2. Off time
  3. Squeeze time
  4. Weld time

Answer (Detailed Solution Below)

Option 4 : Weld time

Welded Joints Question 5 Detailed Solution

Explanation:

Weld Time:

  • It is the time during which welding current is applied to the work in making a weld.
  • It is measured in cycles of line voltage as are all timing functions.
  • One cycle is 1/60 of a second in a 60 Hz power system.

Squeeze Time :

  • It is the time interval between the initial application of the electrode force on the work and the first application of current.
  • Note that this is the process definition.
  • The control definition is the time interval between sequence initiation and beginning of weld current.
  • Squeeze time is necessary to delay the weld current until electrode force has built up to the desired level.

Hold Time:

  • It is the time during which electrode force is maintained on the work after the last impulse of welding current ceases.
  • Hold time is necessary to allow the weld nugget to solidify before releasing the welded parts.

Off Time:

  • It is the time during which the electrodes are off the work.
  • The term is only applicable where the weld cycle is repetitive (control set on “REPEAT”).

Additional Information 

Duty cycle:

  • It is the amount of time during which the transformer will be used for welding under normal loading conditions.
  • It is the time span in successive 10 min interval during which current can be drawn from the transformer, after that there should be a compulsory break otherwise the temperature of its essential components will increase.
  • Usually, a 60% duty cycle is the standard industrial rating.
  • A power source with such a rating can supply its rated output for 6 minutes in every 10-minute interval of its operation.
  • I2D = Constant, where D = Duty cycle and I = Current

Top Welded Joints MCQ Objective Questions

The type of weld represented by the shaded region in the figure is

GATE ME 2018 Set 1 Solutions images satya D 8

  1. groove
  2. spot
  3. fillet
  4. plug

Answer (Detailed Solution Below)

Option 3 : fillet

Welded Joints Question 6 Detailed Solution

Download Solution PDF

For spot welding of 1 mm thick sheet with a current flow time of 0.2 s, the heat generated is 1000 J. If the effective resistance is 200 μΩ, the current required is   

  1. 4000 A
  2. 5000 A
  3. 6000 A
  4. 7000 A

Answer (Detailed Solution Below)

Option 2 : 5000 A

Welded Joints Question 7 Detailed Solution

Download Solution PDF

Concept:

Heat generated (Q) in the spot welding is given by, Q = I2 × R × t

Where I is the flow of current, R is the resistance and the t is the duration for which the current flows

Calculation:

Given, Current flow time t = 0.2 s, Heat generated = 1000 J and, Resistance = 200 μΩ

1000 = I2 × 200 × 10-6 × 0.2

I = 5000 A

Identify the toe crack from the given figure.

F2 Madhuri Engineering 28.07.2022 D2

  1. B
  2. A
  3. C
  4. D

Answer (Detailed Solution Below)

Option 3 : C

Welded Joints Question 8 Detailed Solution

Download Solution PDF

Explanation:

Welding defects:

  • Cracks
  • Cavities
  • Solid inclusions
  • Incomplete fusion
  • Imperfect shape or unacceptable contour

 

Welding cracks:

Fracture-type interruptions either in the weld or in base metal adjacent to the weld.

Serious defect because it is a discontinuity in the metal that significantly reduces strength.

Caused by embrittlement or low ductility of weld and/or base metal combined with high restraint during contraction.

In general, this defect must be repaired.

F2 Madhuri Engineering 28.07.2022 D3

Cavities:

Two defect types, similar to defects found in castings:

1. Porosity - Small voids in weld metal formed by gases entrapped during solidification. Caused by the inclusion of atmospheric gases, sulfur in the weld metal, or surface contaminants.

2. Shrinkage voids - Cavities formed by shrinkage during solidification.

Solid inclusion:

Nonmetallic material is entrapped in the weld metal. A most common form is slag inclusions generated during AW processes that use flux. Instead of floating on top of the weld pool, globules of slag become encased during solidification.

Incomplete fusion:

A weld bead in which fusion has not occurred throughout the entire cross-section of the joint.

In an arc welding process, welding speed is doubled. Assuming all other process parameters to be constant, the cross sectional area of the weld bead will

  1. Increase by 25%
  2. Increase by 50%
  3. Reduce by 25%
  4. Reduce by 50%

Answer (Detailed Solution Below)

Option 4 : Reduce by 50%

Welded Joints Question 9 Detailed Solution

Download Solution PDF

Explanation:

Metal deposit rate (MDR) = Area (A) x Weld Speed (V) = Constant

A1 V1 = A2V2; V2 = 2V1 (given)

\({A_1}{V_1} = {A_2}\left( {2{V_1}} \right) \Rightarrow {A_2} = \frac{{{A_1}}}{2}\)

So cross sectional area reduce by half (50%)

The voltage – Length characteristics of a direct current arc in an arc welding process is V = (100 + 40 L), where l is the length of the arc (in mm) & and V is arc voltage in volts. During a  welding operation, the arc length varies from 1 and 2 mm and the welding current is in the range 200 - 250 A. Assuming linear power source, the short circuit current is__________ A.

Answer (Detailed Solution Below) 423 - 428

Welded Joints Question 10 Detailed Solution

Download Solution PDF

We know that,  \(V = {V_o} - \left( {\frac{{{V_o}}}{{{I_{sc}}}}} \right) \times I\) ……….. (1)

Here,

V = (100 + 40 L)

\(\left. {\begin{array}{*{20}{c}} {\begin{array}{*{20}{c}} {{V_1} = 100 + \left( {40 \times 1} \right) = 140V,}\\ {{V_2} = 100 + \left( {40 \times 2} \right) = 180V,} \end{array}}&{\begin{array}{*{20}{c}} {{I_1} = 250A}\\ {{I_2} = 200A} \end{array}} \end{array}} \right\}\begin{array}{*{20}{c}} {Voltage\;\& \;current\;are\;inversely\;proportional\;} \end{array}\)

Putting the value of V1, V2, I & I2 in the equation

\(\begin{array}{*{20}{c}} { \Rightarrow 180 = {V_o} - \left( {\frac{{{V_o}}}{{{I_{SC}}}}} \right) \times 200 - - - - - \left( 2 \right)\;}\\ { \Rightarrow 140 = {V_o} - \left( {\frac{{{V_o}}}{{{I_{SC}}}}} \right) \times 250 - - - - - \left( 3 \right)}\\ {\overline { \Rightarrow 40 = \left( {\frac{{{V_o}}}{{{I_{SC}}}}} \right) \times \left( {250 - 200} \right)} } \end{array}\)  

We got the above relation by subtracting equation 2 and 3

By solving \(\left( {\frac{{{V_o}}}{{{I_{sc}}}}} \right) = \frac{4}{5}\)       ----(4)

Using (4) in (2) we have

\(\Rightarrow 180 = {V_o} - \left( {\frac{4}{5}} \right) \times 200\)

⇒ Vo = 180 + 160 ⇒ Vo = 340V      ----(5)

using (5) in (4) we have

\(\frac{{{V_o}}}{{{I_{sc}}}} = \frac{4}{5} \Rightarrow {I_{sc}} = \frac{5}{4} \times {V_o} = \frac{5}{4} \times 340 = 425\;A\)

A plate 100 mm wide and 10 mm thick is welded to another plate by means of a double parallel fillet weld. The welding is done along the width of the plate. The plates are subjected to a force of 75 kN. The maximum strength of the joint in tension and shear stress is 80 MPa and 60 MPa respectively. The length of the weld without adding the length for starting and stoppage will approximately be: 

  1. 35.2 mm
  2. 44.2 mm
  3. 88.4 mm
  4. > 90.0 mm

Answer (Detailed Solution Below)

Option 3 : 88.4 mm

Welded Joints Question 11 Detailed Solution

Download Solution PDF

Concept:

In Parallel Fillet Weld failure occurs because of shear and the Strength of Parallel Fillet Weld is given by

\(\tau = \frac{P}{tl} = \frac{P}{0.707nhl}\)

where \(\tau\) = Shear Strength of Joint, P = Force Acting on the Plate, h = leg of the weld, t = throat of the weld, l = length of the weld, n = no of weld

Calculation:

Given:

h = 10 mm, b = 100 mm, P = 75 kN, \(\tau\) = 60 MPa, \(\sigma\) = 80 MPa, n = 2 (Double Parallel Fillet Weld)

MD final images Q6

In a double parallel fillet weld, two lines of welding are to be provided. Hence each line shares a load of 

\(F = \frac{P}{2 } = \frac{75}{2}\)

F = 37.5 kN = 37500 N

\(F = 0.707\tau nhl\)

37500 = 0.707 × 60 × 106  × 10 × 10-3 × l

l = 88.4 mm

Consider a single V-groove butt welded joint between two plates of the same thickness equal to 6 mm and the same width of 60 mm is subjected to a tensile force of 36 kN. Assuming that the weld throat dimension is the same as the thickness of the plate, then the average normal stress induced in the joint is equal to?

  1. 50 MPa
  2. 100 MPa
  3. 150 MPa
  4. 200 MPa

Answer (Detailed Solution Below)

Option 1 : 50 MPa

Welded Joints Question 12 Detailed Solution

Download Solution PDF

Concept:

The weld strength formula for V-groove or double butt joint is:

\(P = (t_1+t_2)\times l\times σ_t\)

where t1 and t2 are the thickness of the plate, l is the length of the plate, P is the tensile force, and σt is the normal stress.

Calculation:

Given:

t1 = t2 = 6 mm, l = 60 mm, P = 36 kN

\(\sigma_t = \frac{P}{2t\times l}\)

\(\sigma_t = \frac{36000}{2\times 0.6\times 6} = 50 \ MPa\)

Spot welding of two steel sheets each 2 mm thick is carried out successfully by passing 4 kA of current for 0.2 seconds through the electrodes. The resulting weld nugget formed between the sheets is 5 mm in diameter. Assuming cylindrical shape for the nugget, the thickness of the nugget is _______ mm.

Latent heat of fusion for steel

1400 kJ/kg

Effective resistance of the weld joint

200 μΩ

Density of steel

8000 kg/m3

Answer (Detailed Solution Below) 2.85 - 2.95

Welded Joints Question 13 Detailed Solution

Download Solution PDF

Concept:

Calculate the heat supplied for melting and heat required for melting.

And then equating both of them will give you the thickness of nugget.

Calculation:

Given:

thickness of steel sheets = 2 mm.

I = 4 kA, time (t) = 0.2 seconds.

Diameter of Nugget = 5 mm

Assuming cylindrical shape of Nugget.

Volume \(= \frac{\pi }{4}{D^2}{t_n}\), where tn → Thickness of Nugget

Now,

Heat required to melt the above volume of Nugget = Heat required to melt 1 kg × Total mass (m)

∵ density (ρ) = mass/Volume

∴ m = ρ × volume

∴ Heat required to melt volume of nugget (Q)= Heat required to melt 1 kg × ρ × volume

\(\therefore {\rm{Q}} = \left( {1400} \right) \times \frac{{\rm{\pi }}}{4}{\rm{\;}}{{\rm{D}}^2}{{\rm{t}}_{\rm{n}}} \times \left( {8000} \right){\rm{\;kJ}}\)

And

Heat supplied = I2Rt= (4× 103)2 × (200 × 10-6) × 0.2

Heat supplied = 640 J.

Equating the heat calculated by two methods:

\(640 = \left( {1400} \right)\frac{\pi }{4}{\left( {0.005} \right)^2}{t_n}\left( {8000} \right) \times {10^3}\)

640 = (219.911 × 103) tn

tn = 2.91 × 10-3 m

∴ tn = 2.91 mm.

The symbol qImage680e08bb0c0ca2cc55c827dd refers to:

  1. Single Fillet weld
  2. Square butt weld
  3. Seam weld
  4. Single V-butt weld

Answer (Detailed Solution Below)

Option 1 : Single Fillet weld

Welded Joints Question 14 Detailed Solution

Download Solution PDF

Explanation:

Welding symbol:

  • The arrow of the welding symbol indicates the point at which the weld is to be made and the line connecting the arrow to the reference line is always at an angle.
  • Whenever the basic weld symbol is placed below the reference line, the weld is made on the side where the arrow points (referred to as the arrow side).
  • Whenever the basic symbol is placed above the reference line, the weld is to be made on the other side of the joint.
  • The symbol for fillet weld is 3

Welder 20 10Q Revised Hindi - Final 3

  • Figure: (a) Fillet weld symbols shown on the bottom side of the reference line indicates that the weld is located in the same position where the arrow points.
  • Figure: (b) Fillet weld symbols shown on the upper side of the reference line indicates that the weld is on the opposite side where the arrow points.

∵ there is nothing mention about the arrow side or other side, ∴ single fillet weld will be the required answer.

Additional Information

Some of the common welding symbols is given below.

weld symbol1

111

2222

Welded Joints Question 15:

Joggled welded joints are used ______.

  1. where longitudinal shear is present
  2. where sever loading is encountered and the upper surface of both pieces must be in the same plane
  3. to join two pieces of metal in the same manner as rivet joint metals
  4. there is nothing called Jogged welded joint

Answer (Detailed Solution Below)

Option 2 : where sever loading is encountered and the upper surface of both pieces must be in the same plane

Welded Joints Question 15 Detailed Solution

Concept:

  • Joggle joints are used where a strong joint on the flat surface is needed to join two pieces of sheet metal.
  • Generally, there are hand tools available to put the joggle into the sheet metal.
  • Joggled welded joints are used where severe loading is encountered, and the upper surface of both pieces must be in the same plane.

 

F2 S.S Madhu 18.02.20 D3           F2 S.S Madhu 18.02.20 D5

F2 S.S Madhu 18.02.20 D4

F2 S.S Madhu 18.02.20 D1

F2 S.S Madhu 18.02.20 D2

Get Free Access Now
Hot Links: teen patti sequence teen patti dhani teen patti gold apk download teen patti master 2024