Download Solution PDFWhat does PERT stand for in Industrial Management?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFConcept:
- Network models can be used as an aid in scheduling large complex projects that consist of many activities.
- If the duration of each activity is known with certainty, then the Critical Path Method (CPM) can be used to determine the length of time required to complete a project.
- If the duration of the activities is not known with certainty, the Program Evaluation and Review Technique (PERT) can be used to estimate the probability that the project will be completed by a given deadline.
- Difference between PERT and CPM (Critical Path Method)
PERT |
CPM |
1. Probabilistic approach |
1. Deterministic approach |
2. Three-time estimate |
2. One - time estimate |
3. Event oriented network model |
3. Activity-oriented network model |
4. The slack concept is used |
4. Float concept is used |
5. Project crashing is not possible |
5. Project crashing is possible |
6. Deals with probabilistic time estimates |
6. Deals with deterministic time estimates |
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.