In critical path method of construction planning, free float can be

1. greater than total float

2. greater than independent float

3. equal to total float

4. less than independent float.

Of these statements,

This question was previously asked in
OSSC JE Civil Mains (Re-Exam) Official Paper: (Held On: 3rd Sept 2023)
View all OSSC JE Papers >
  1. only 1 and 4 are correct
  2. only 2 and 3 are correct
  3. only 2 and 4 are correct
  4. only 1 and 2 are correct

Answer (Detailed Solution Below)

Option 2 : only 2 and 3 are correct
Free
OSSC JE Civil Geo-technical Engineering Mock Test
20 Qs. 40 Marks 36 Mins

Detailed Solution

Download Solution PDF

Explanation:

In the Critical Path Method (CPM) of construction planning, the following concepts about floats are essential:

  1. Free Float (FF): This is the amount of time an activity can be delayed without affecting the start of the subsequent activity.

  2. Total Float (TF): This is the amount of time an activity can be delayed without delaying the overall project completion time.

  3. Independent Float (IF): This is the amount of time an activity can be delayed without affecting either its preceding or succeeding activities.

Understanding the Relationships:

  1. Free Float can never be greater than the Total Float. The total float represents the maximum delay an activity can have before impacting the project’s end, while free float only considers the effect on the next activity. Hence, FF ≤ TF.

  2. Free Float can be greater than or equal to the Independent Float. The independent float is a very restricted float that ensures no effect on any other activities, so it can often be smaller than free float. Therefore, FF ≥ IF.

  3. Free Float can be equal to Total Float when there are no other dependent activities affected by a delay. In this case, delaying the activity only affects its immediate successor.

  4. Free Float can never be less than Independent Float because independent float is the most restricted form of float.

Conclusion:

  • Statement 1 is incorrect (free float cannot be greater than total float).

  • Statement 2 is correct (free float can be greater than independent float).

  • Statement 3 is correct (free float can be equal to total float).

  • Statement 4 is incorrect (free float cannot be less than independent float).

Latest OSSC JE Updates

Last updated on Jun 4, 2025

-> OSSC JE Preliminary Fiinal Answer Key 2025 has been released. Applicants can raise objections in OSSC JE answer key till 06 June 2025.

-> OSSC JE prelim Exam 2025 was held on 18th May 2025.(Advt. No. 1233/OSSC ).

-> The OSSC JE 2024 Notification was released for 759 vacancies through OSSC CTSRE 2024.

-> The selection is based on the written test. This is an excellent opportunity for candidates who want to get a job in the Engineering sector in the state of Odisha.

-> Candidates must refer to the OSSC JE Previous Year Papers to understand the type of questions in the examination. 

Hot Links: teen patti joy vip teen patti gold apk download teen patti casino download teen patti comfun card online