Full Reservoir Level (FRL) is:

This question was previously asked in
JKSSB JE (Civil) Official Paper (Held On: 19 Nov, 2023)
View all JKSSB JE Papers >
  1. The maximum elevation to which reservoir water surface will rise during normal operating conditions
  2. The maximum level to which reservoir water will rise during worst design flood
  3. The normal operating level in a reservoir
  4. Both (A) and (C)

Answer (Detailed Solution Below)

Option 4 : Both (A) and (C)
Free
JKSSB JE Civil RCC Structures Mock Test
1.2 K Users
20 Questions 20 Marks 20 Mins

Detailed Solution

Download Solution PDF

Explanation:

  • The maximum elevation to which reservoir water surface will rise during normal operating conditions
  • This defines the maximum water level that a reservoir is allowed to reach during standard or intended usage.

  • It determines the design and operational limits of various hydraulic structures like spillways, gates, and power intakes.

  • Beyond FRL, water is not normally stored, and any additional inflow is routed through spillways.

  • The normal operating level in a reservoir

  • FRL is considered the target water level during the reservoir’s routine operations.

  • It ensures optimum storage for purposes such as irrigation, water supply, hydropower, and navigation.

  • Operators aim to maintain this level to balance demand and storage without flooding or loss of utility.

  • In seasonal reservoirs, water is typically stored up to FRL during monsoon and drawn down post-monsoon.

 Additional Information

Full Reservoir Level (FRL):

  • The maximum elevation the reservoir water surface is allowed to reach during normal operations.

  • Used for designing the capacity of the reservoir, penstocks, intake structures, etc.

Maximum Water Level (MWL):

  • The highest level reached during design floods or emergency conditions, which may be above FRL.

  • Determines the top of dam or freeboard design.

Dead Storage Level:

  • The portion of the reservoir below the lowest outlet, not usable under gravity flow.

Live Storage:

  • The volume of water stored between the dead storage level and FRL, usable for operational purposes.

Latest JKSSB JE Updates

Last updated on Jul 1, 2025

-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been rescheduled on its official website. 

-> JKSSB JE exam will be conducted on 31st August (Civil), and on 24th August 2025 (Electrical).

-> JKSSB JE application form correction facility has been started. Candidates can make corrections in the JKSSB recruitment 2025 form from June 23 to 27. 

-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering. 

-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025. 

-> JKSSB JE Online Application form will be activated from 18th May 2025 to 16th June 2025 

-> Candidates who are preparing for the exam can access the JKSSB JE syllabus PDF from official website of JKSSB.

-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.

-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.

Get Free Access Now
Hot Links: online teen patti real money teen patti glory teen patti win