Question
Download Solution PDFCritical path in PERT -
This question was previously asked in
UKPSC JE Civil 8 May 2022 Official Paper-I
Answer (Detailed Solution Below)
Option 4 : is always longest
Free Tests
View all Free tests >
UKPSC JE CE Full Test 1 (Paper I)
1.8 K Users
180 Questions
360 Marks
180 Mins
Detailed Solution
Download Solution PDFExplanation:
Critical Path:
- From the activity network representation, it can be analysed that the minimum time to complete the project is the maximum of all paths from start to finish.
- So, the longest path will represent the critical path for the network, and it will represent the minimum possible duration required to complete the project.
- The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.
Last updated on Mar 26, 2025
-> UKPSC JE Notification for 2025 will be out soon!
-> The total number of vacancies along with application dates will be mentioned in the notification.
-> The exam will be conducted to recruit Junior Engineers through Uttarakhand Public Service Commission.
-> Candidates with an engineering diploma in the concerned field are eligible.
-> The selection process includes a written exam and document verification. Prepare for the exam with UKPSC JE Previous Year Papers.