A project takes 20 days along the critical path and has a standard deviation of 4 days. How many days does it take to complete the project?

This question was previously asked in
JKSSB JE (Civil) Official Paper (Held On: 19 Nov, 2023)
View all JKSSB JE Papers >
  1. 20 days
  2. 24 days
  3. 18 days
  4. 16 days

Answer (Detailed Solution Below)

Option 2 : 24 days
Free
JKSSB JE Civil RCC Structures Mock Test
20 Qs. 20 Marks 20 Mins

Detailed Solution

Download Solution PDF

Concept:

Probability can be calculated by using probability factor (Z) which is defined as, 

where, Ts = Schedule completion time

Te = Expected completion time

 Standard deviation

Z = Probability factor depending on probability

Calculation:

Given: Te = 20 days, 

For 84.13 %, Z = 1

Latest JKSSB JE Updates

Last updated on Jul 1, 2025

-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been rescheduled on its official website. 

-> JKSSB JE exam will be conducted on 31st August (Civil), and on 24th August 2025 (Electrical).

-> JKSSB JE application form correction facility has been started. Candidates can make corrections in the JKSSB recruitment 2025 form from June 23 to 27. 

-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering. 

-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025. 

-> JKSSB JE Online Application form will be activated from 18th May 2025 to 16th June 2025 

-> Candidates who are preparing for the exam can access the JKSSB JE syllabus PDF from official website of JKSSB.

-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.

-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.

Hot Links: teen patti bodhi teen patti app online teen patti